2017-08-28:
In June-2017 we started the construction of production and warehouse hall with office space for Erae Poland Sp. z o.o. in Zabrze.
The design assumes construction of building of area about 11,500 m2 as well as roads and parking with total area of about 11,000 m2.
At the end of August-2017 the progress of the works is about 50%, and planned deadline for completion is January-2018.