Starting from August 2021, we are executing works for 3rd & 4th phases of the construction of a lithium-ion battery separator factory for SK Hi-Tech Battery Materials Poland Sp. z o.o. in Dąbrowa Górniczna as part of the Europe Project Phase-3&4.
We perform the works as a subcontractor of the Korean giant SK ECOENGINEERING Co. Ltd.
Our scope of works covers:
- foundation work for Main Process Bulding MPB-1,
- temporary fence and gate,
- IBL building SOG & reinforced concrete work,
- coring and finishing work,
- smoke curtain work.
At the same time, from the very beginning we provide office facilities on the construction site for the Investor and the General Contractor.