Current progress of Erae Poland Factory construction in Zabrze

2017-10-09:
We hereby present the current progress on the construction of production and warehouse hall with office space for Erae Poland Sp. z o.o. in Zabrze.
We started construction works in June-2017, and as on the end of September-2017 a two-third part of a whole investment is finished !

Planned deadline for completion is January-2018.

Progress from previous time periods:
2017-08-28: